GH's financial management system did not meet federal standards. In particular: Procurements did not meet the competition or cost and price analysis requirements of the Code of Federal Regulations in 40 CFR 30.43 and 30.45. The contract administration system did not meet the requirements of 40 CFR 30.47. Unallowable costs were not segregated and financial management data were not properly supported as required under 40 CFR §30.21 and 2 CFR Part 230. Labor charges did not comply with the requirements of 2 CFR Part 230. Cash draws did not meet immediate cash needs requirement and were not properly documented as required under 40 CFR 30.22 and §30.21. As a result of the issues noted, we questioned $1,615,343 of the $2,250,031 claimed under the CA. In addition, due to lack of adequate documentation from GH, we were unable to determine whether GH accomplished the objective of the CA or met the job reporting requirements of Recovery Act Section 1512.

Vis mere
  • Sprog:
  • Engelsk
  • ISBN:
  • 9781500640804
  • Indbinding:
  • Paperback
  • Sideantal:
  • 38
  • Udgivet:
  • 1. august 2014
  • Størrelse:
  • 216x280x2 mm.
  • Vægt:
  • 113 g.
  • 2-3 uger.
  • 16. december 2024
På lager
Forlænget returret til d. 31. januar 2025

Normalpris

  • BLACK FRIDAY
    : :

Medlemspris

Prøv i 30 dage for 45 kr.
Herefter fra 79 kr./md. Ingen binding.

Beskrivelse af Examination of Costs Claimed Under American Recovery and Reinvestment Act Cooperative Agreement 2A-97706701 Awarded to Grace Hill Settlement House, St. Louis, Missouri

GH's financial management system did not meet federal standards. In particular: Procurements did not meet the competition or cost and price analysis requirements of the Code of Federal Regulations in 40 CFR 30.43 and 30.45. The contract administration system did not meet the requirements of 40 CFR 30.47. Unallowable costs were not segregated and financial management data were not properly supported as required under 40 CFR §30.21 and 2 CFR Part 230. Labor charges did not comply with the requirements of 2 CFR Part 230. Cash draws did not meet immediate cash needs requirement and were not properly documented as required under 40 CFR 30.22 and §30.21. As a result of the issues noted, we questioned $1,615,343 of the $2,250,031 claimed under the CA. In addition, due to lack of adequate documentation from GH, we were unable to determine whether GH accomplished the objective of the CA or met the job reporting requirements of Recovery Act Section 1512.

Brugerbedømmelser af Examination of Costs Claimed Under American Recovery and Reinvestment Act Cooperative Agreement 2A-97706701 Awarded to Grace Hill Settlement House, St. Louis, Missouri



Find lignende bøger
Bogen Examination of Costs Claimed Under American Recovery and Reinvestment Act Cooperative Agreement 2A-97706701 Awarded to Grace Hill Settlement House, St. Louis, Missouri findes i følgende kategorier:

Gør som tusindvis af andre bogelskere

Tilmeld dig nyhedsbrevet og få gode tilbud og inspiration til din næste læsning.